FPSO ANOA Conceptual Dry-Dock Study (2013)

Natuna 1

FPSO ANOA Conceptual Dry-Dock Study (2013)

  • Assessment on availability/market of dry-docks in S.E.A region (Singapore, Indonesia).
  • Conceptual definition of dry-dock scope based on the evaluation of the previous inspection record (UWILD, tank cleaning etc.) Review of potential dry docks commercial proposals verses alternatives.
  • Assessment on availability/market of vessel replacement in region.
  • Conceptual definition of replacement logic, sequence and scope.
  • Cost estimate for the entire cycle of the project including, dry-dock, replacement, de-mobilisation and mobilisation costs etc. Additional requirements for tugs, towing vessels, towage required and bollard pull study.
  • Level-1 schedule of the entire cycle of the project including government approvals and expected tender process.