MWS for Cendor Phase 2 Field Development Project
[su_list icon="icon: certificate" icon_color="#fff"]
- The Cendor Phase II and West Desaru project installation scope of work includes the following items:
- • The Installation of Jacket and Topside:
- - CDW-B Jacket (approx. 1,600 MT)
- - CDW-B Topside (approx. 1,240 MT)
- - CDW-C Jacket (approx. 1,600 MT)
- - CDW-C Topside (approx. 1,161 MT)
- • The Installation of Rigid Pipeline:
- - 1 x 8” 13.7km West Desaru Pipeline (MOPU to PLET)
- - 2 x 8” 1.6km WI & GL Rigid Pipelines (CDW-B to PLET)
- - 2 x 8” 3.3km WI & GL Rigid Pipelines (CDW-C to PLET)
- • The Installation of Flexible Flowline:
- - 1 x 8” 2.6km Flexible Flowline (WD PLET to FSO)
- • The Installation of FPSO Mooring System:
- - 12 x Mooring Piles and Chains
- - Proof load Mooring Chain to 400T
- • The Installation of 2 x Mid Water Arch (MWA) (approx. 800MT each)
- • The Installation of 3 x PLET (approx. 26MT each)
- • The Installation of Flexible Riser:
- - 1 x 8” 0.3km (West Desaru MOPU)
- • The Installation of Jacket and Topside:
- Acting on behalf of the insurance underwriter, IMEC has successfully complete their role as MWS for this project without any insurance claims against the project policies
- IMEC has also been awarded with ‘Certificate of Appreciation’ from Petrofac for the completion of this project without LTI.